Admin Building Parking Lot Restoration
Project Owner
- Gretchen Bechtel — Project Contact
- 15470 Flight Path Dr, Brooksville, FL 34604
- (352) 754-4000 Ext. 24156
- gbechtel@co.hernando.fl.us
Contractor
- Arthur Wilmoth — Senior Project Manager
- Joe Santerelli — Project Manager (Primary On-Site)
- 10701 N Nebraska Ave, Tampa, FL 33612
- 813-853-6597 | CBC1267421
Project Scope Summary
- Mill, repair, and resurface existing parking lot sections
- Install Poly Guard NW-75 membrane (anti-reflective cracking)
- 2" SP-12.5 asphalt w/ bituminous tack coat
- Seal coat existing asphalt (Section C)
- Concrete sidewalk & dumpster pad work
- ADA compliance: warning mats, signs, signposts
- Wheel stops, layout, paint, and striping
Key Dates & Permits
- Pre-Construction Meeting: July 9, 2026 — 10:00 AM
- NPDES Permit (stormwater / erosion control)
- Hernando County Building Permit
- Performance & Payment Bond on file
- ~2 weeks lead time after NTP for material orders
- FDOT specs for asphalt & tack coat
Site Inspection & Coordination
- Hernando County BOCC representative — daily coordination
- Active county facility — phased work to maintain operations
- Daily sign-in sheets posted at staging area
- Weekly safety meetings (Toolbox Talks)
- SWPPP inspections per NPDES requirements
MOT & Safety
- Work hours 7 AM – 5 PM weekdays
- Cones & barriers mark all work zones; phased lot closures
- Full PPE (hardhats, hi-vis vests w/ FF logo, safety boots)
- Spotters, backup alarms, OSHA-compliant operations
- Daily site cleanup; drive lanes restored end of day
- Public access maintained to remaining open lots
Scope of Work — Phase Breakdown
Sequenced by week — concrete & drainage first so the perimeter is ready when the asphalt is torn up. Weeks 6 & 7 are contingency for rain / delays.
Week 1 — Site Concrete + Drainage
- Install replacement concrete sidewalks (Section A.1 + elevation match)
- Install ~12.5′ of 6″ sch 40 PVC drainage / culvert pipe (tapered)
- Pour concrete dumpster pad
- Saw cutting for asphalt / concrete boundaries
- Regrading of affected areas (fill dirt, sod at culvert)
- SWPPP (silt fence, inlet protection) verified in place before disturbance
Week 2 — Asphalt Demo + Base Work
- Asphalt demo — Lot B
- Asphalt demo — back of Lot C
- Clearing & grubbing in Lot C extension area (1,100 SF)
- Base work — limerock base repair, regrade, compaction
- Sections A & B tarmac repairs (spot fixes ahead of Poly Guard)
- Section C base-layer repair & regrade for elevation match
Week 3 — Crack Fill + Concrete Repairs
- Crack filling / sealing across Lots A, B, C
- Larger concrete repairs beyond scope of crack fill
- Prep any remaining sub-base issues discovered during Week 2
- Continued daily SWPPP inspections
Week 4 — Poly Guard NW-75 + Paving
- Install Poly Guard NW-75 membrane over Sections A & B
- Install 2″ SP-12.5 asphalt w/ bituminous tack coat (0.07 gal/SY)
- Asphalt on 1,100 SF Lot C extension and 6,941 SF area
- Rolling & compaction per FDOT spec
- Cure time before opening to traffic
Week 5 — Striping, Seal Coat & Wheel Stops
- Lot marking — layout, paint, and striping (stalls, arrows, ADA markings)
- Seal coat existing asphalt on Section C
- Install new wheel stops (includes removal of old wheel stops)
- Install ADA detectable warning mats on sidewalks
- Install ADA signs & signposts
- SWPPP take-down (silt fence, inlet protection)
- Site walk / final inspection with County
- As-built submission
Weeks 6 & 7 — Contingency
- Reserved for weather delays — primarily rain during paving / seal coat
- Reserved for unforeseen sub-base or utility conflicts
- Reserved for any punch-list items after the Week 5 site walk
- Program will close as early as Week 5 — likely 5 to 6 weeks total
Project Schedule
| Task | Days | Wk 1 | Wk 2 | Wk 3 | Wk 4 | Wk 5 | Wk 6 (Cont.) | Wk 7 (Cont.) | ||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | ||
| WEEK 1 — SITE CONCRETE + DRAINAGE | ||||||||||||||||||||||||||||||||||||
| Saw Cut + SWPPP Verify | 1 | |||||||||||||||||||||||||||||||||||
| Culvert Pipe Install (6" PVC) | 2 | |||||||||||||||||||||||||||||||||||
| Concrete Sidewalks (A.1 + Elev.) | 3 | |||||||||||||||||||||||||||||||||||
| Concrete Dumpster Pad | 1 | |||||||||||||||||||||||||||||||||||
| Regrading (Culvert + Sod) | 1 | |||||||||||||||||||||||||||||||||||
| WEEK 2 — ASPHALT DEMO + BASE WORK | ||||||||||||||||||||||||||||||||||||
| Asphalt Demo — Lot B | 2 | |||||||||||||||||||||||||||||||||||
| Asphalt Demo — Back of Lot C | 2 | |||||||||||||||||||||||||||||||||||
| Clearing & Grubbing — Lot C Ext. | 1 | |||||||||||||||||||||||||||||||||||
| Base Work / Limerock Repair | 2 | |||||||||||||||||||||||||||||||||||
| Sections A & B Tarmac Repairs | 1 | |||||||||||||||||||||||||||||||||||
| WEEK 3 — CRACK FILL + CONCRETE REPAIRS | ||||||||||||||||||||||||||||||||||||
| Crack Fill — Lots A, B, C | 3 | |||||||||||||||||||||||||||||||||||
| Larger Concrete Repairs | 2 | |||||||||||||||||||||||||||||||||||
| WEEK 4 — POLY GUARD NW-75 + PAVING + CURE | ||||||||||||||||||||||||||||||||||||
| Poly Guard NW-75 Install | 2 | |||||||||||||||||||||||||||||||||||
| 2" SP-12.5 Asphalt Pave | 2 | |||||||||||||||||||||||||||||||||||
| Cure Time | 1 | |||||||||||||||||||||||||||||||||||
| WEEK 5 — STRIPING, SEAL COAT & WHEEL STOPS | ||||||||||||||||||||||||||||||||||||
| Seal Coat — Section C | 1 | |||||||||||||||||||||||||||||||||||
| Lot Marking / Striping | 2 | |||||||||||||||||||||||||||||||||||
| Wheel Stops (New + Remove Old) | 1 | |||||||||||||||||||||||||||||||||||
| ADA Mats + Signs + Signposts | 1 | |||||||||||||||||||||||||||||||||||
| SWPPP Take-Down + Site Walk | 1 | |||||||||||||||||||||||||||||||||||
| Daily Cleaning | — | |||||||||||||||||||||||||||||||||||
| WEEKS 6 & 7 — CONTINGENCY (RAIN / DELAY) | ||||||||||||||||||||||||||||||||||||
| Contingency Buffer | 10 | |||||||||||||||||||||||||||||||||||
Photo Timeline
Before, during, and after documentation. Admin can upload photos from the Admin panel.
No photos yet
Photos will appear here as the project progresses.
Project Documents
Daily sign-in sheets, weekly safety meetings, and SWPPP (Stormwater Pollution Prevention Plan) documents. Admin uploads from the Admin panel.
No documents yet
Documents will appear here as they are uploaded.
Project Progress
No updates yet
Progress updates will appear here once the project begins.
Field Notes
Observations, issues, RFIs, daily logs — added during construction via the Admin panel.
No field notes yet
Admin Panel
Post Progress Update
Click or drag photos here
Upload Document
Daily sign-in sheets, safety meeting notes, SWPPP inspection reports. PDFs preferred; PNG/JPG/DOC also accepted.
Click or drag file here (PDF, image, or Office doc)
Manage Documents
View or delete uploaded documents.
No documents uploaded yet.
Upload Photos
Up to 5 photos at a time. Auto-compressed for fast upload from phone.
Update Progress
Add Field Note
Manage Field Notes
No field notes yet.
Manage Updates
No updates posted yet.