Admin Building Parking Lot Restoration

Hernando County BOCC | 15470 Flight Path Dr, Brooksville, FL 34604 | Proposal #20260089
Program Length
7 Weeks
5 Work + 2 Contingency (Max)
Target Close
5–6 Wks
Weather Permitting
Work Phases
5
Sequential Weeks
Surface Area
~8,000 SF
New Asphalt
Key Material
Poly Guard
NW-75 Membrane
Overall Progress
0%

Project Owner

Hernando County BOCC
  • Gretchen Bechtel — Project Contact
  • 15470 Flight Path Dr, Brooksville, FL 34604
  • (352) 754-4000 Ext. 24156
  • gbechtel@co.hernando.fl.us

Contractor

Firm Foundations Asphalt & Concrete LLC
  • Arthur Wilmoth — Senior Project Manager
  • Joe Santerelli — Project Manager (Primary On-Site)
  • 10701 N Nebraska Ave, Tampa, FL 33612
  • 813-853-6597 | CBC1267421

Project Scope Summary

Lots A, B, C + Extension Areas
  • Mill, repair, and resurface existing parking lot sections
  • Install Poly Guard NW-75 membrane (anti-reflective cracking)
  • 2" SP-12.5 asphalt w/ bituminous tack coat
  • Seal coat existing asphalt (Section C)
  • Concrete sidewalk & dumpster pad work
  • ADA compliance: warning mats, signs, signposts
  • Wheel stops, layout, paint, and striping

Key Dates & Permits

Contract Terms
  • Pre-Construction Meeting: July 9, 2026 — 10:00 AM
  • NPDES Permit (stormwater / erosion control)
  • Hernando County Building Permit
  • Performance & Payment Bond on file
  • ~2 weeks lead time after NTP for material orders
  • FDOT specs for asphalt & tack coat

Site Inspection & Coordination

On-Site Contacts
  • Hernando County BOCC representative — daily coordination
  • Active county facility — phased work to maintain operations
  • Daily sign-in sheets posted at staging area
  • Weekly safety meetings (Toolbox Talks)
  • SWPPP inspections per NPDES requirements

MOT & Safety

Active County Facility
  • Work hours 7 AM – 5 PM weekdays
  • Cones & barriers mark all work zones; phased lot closures
  • Full PPE (hardhats, hi-vis vests w/ FF logo, safety boots)
  • Spotters, backup alarms, OSHA-compliant operations
  • Daily site cleanup; drive lanes restored end of day
  • Public access maintained to remaining open lots

Scope of Work — Phase Breakdown

Sequenced by week — concrete & drainage first so the perimeter is ready when the asphalt is torn up. Weeks 6 & 7 are contingency for rain / delays.

Week 1 — Site Concrete + Drainage

Perimeter Work While Lot Is Still Open
  • Install replacement concrete sidewalks (Section A.1 + elevation match)
  • Install ~12.5′ of 6″ sch 40 PVC drainage / culvert pipe (tapered)
  • Pour concrete dumpster pad
  • Saw cutting for asphalt / concrete boundaries
  • Regrading of affected areas (fill dirt, sod at culvert)
  • SWPPP (silt fence, inlet protection) verified in place before disturbance
Duration: Week 1 | Perimeter concrete + drainage before demo

Week 2 — Asphalt Demo + Base Work

Lot B, Back of Lot C, and Lot C Extension
  • Asphalt demo — Lot B
  • Asphalt demo — back of Lot C
  • Clearing & grubbing in Lot C extension area (1,100 SF)
  • Base work — limerock base repair, regrade, compaction
  • Sections A & B tarmac repairs (spot fixes ahead of Poly Guard)
  • Section C base-layer repair & regrade for elevation match
Duration: Week 2 | Demo + base ready for Poly Guard

Week 3 — Crack Fill + Concrete Repairs

Lots A, B & C
  • Crack filling / sealing across Lots A, B, C
  • Larger concrete repairs beyond scope of crack fill
  • Prep any remaining sub-base issues discovered during Week 2
  • Continued daily SWPPP inspections
Duration: Week 3 | Repair before overlay

Week 4 — Poly Guard NW-75 + Paving

Membrane Install, Asphalt, Cure
  • Install Poly Guard NW-75 membrane over Sections A & B
  • Install 2″ SP-12.5 asphalt w/ bituminous tack coat (0.07 gal/SY)
  • Asphalt on 1,100 SF Lot C extension and 6,941 SF area
  • Rolling & compaction per FDOT spec
  • Cure time before opening to traffic
Duration: Week 4 | Membrane + full pave + cure

Week 5 — Striping, Seal Coat & Wheel Stops

Final Restoration
  • Lot marking — layout, paint, and striping (stalls, arrows, ADA markings)
  • Seal coat existing asphalt on Section C
  • Install new wheel stops (includes removal of old wheel stops)
  • Install ADA detectable warning mats on sidewalks
  • Install ADA signs & signposts
  • SWPPP take-down (silt fence, inlet protection)
  • Site walk / final inspection with County
  • As-built submission
Duration: Week 5 | Striping + seal + ADA + closeout

Weeks 6 & 7 — Contingency

Rain / Delay Buffer
  • Reserved for weather delays — primarily rain during paving / seal coat
  • Reserved for unforeseen sub-base or utility conflicts
  • Reserved for any punch-list items after the Week 5 site walk
  • Program will close as early as Week 5 — likely 5 to 6 weeks total
Duration: Weeks 6–7 (up to 10 work days) | Contingency only, not scheduled work

Project Schedule

📅
Pre-Construction Meeting: July 9, 2026 — 10:00 AM
From NTP, ~2 weeks lead time to pull permits (NPDES + Building), order materials (Poly Guard NW-75, SP-12.5 asphalt, concrete, ADA hardware, sod), and schedule subcontractors. Schedule below runs by week starting Week 1 of active work. Weeks 6 & 7 are contingency for rain / delays — target close is 5–6 weeks.
Program Length
7 Weeks
Maximum
Active Work
5 Weeks
25 Work Days
Contingency
2 Weeks
10 Days Rain/Delay
Target Close
5–6 Wks
Weather Permitting
Start After NTP
~10 Days
Material Lead Time
Task Days Wk 1Wk 2Wk 3Wk 4Wk 5Wk 6 (Cont.)Wk 7 (Cont.)
12345 678910 1112131415 1617181920 2122232425 2627282930 3132333435
WEEK 1 — SITE CONCRETE + DRAINAGE
Saw Cut + SWPPP Verify1
Culvert Pipe Install (6" PVC)2
Concrete Sidewalks (A.1 + Elev.)3
Concrete Dumpster Pad1
Regrading (Culvert + Sod)1
WEEK 2 — ASPHALT DEMO + BASE WORK
Asphalt Demo — Lot B2
Asphalt Demo — Back of Lot C2
Clearing & Grubbing — Lot C Ext.1
Base Work / Limerock Repair2
Sections A & B Tarmac Repairs1
WEEK 3 — CRACK FILL + CONCRETE REPAIRS
Crack Fill — Lots A, B, C3
Larger Concrete Repairs2
WEEK 4 — POLY GUARD NW-75 + PAVING + CURE
Poly Guard NW-75 Install2
2" SP-12.5 Asphalt Pave2
Cure Time1
WEEK 5 — STRIPING, SEAL COAT & WHEEL STOPS
Seal Coat — Section C1
Lot Marking / Striping2
Wheel Stops (New + Remove Old)1
ADA Mats + Signs + Signposts1
SWPPP Take-Down + Site Walk1
Daily Cleaning
WEEKS 6 & 7 — CONTINGENCY (RAIN / DELAY)
Contingency Buffer10
SWPPP / Erosion
Drainage / Culvert
Concrete / ADA
Grading / Base
Asphalt Demo
Crack Fill
Paving / Cure
Seal Coat
Striping
Daily Cleaning
Site Walk / Inspection
Contingency

Photo Timeline

Before, during, and after documentation. Admin can upload photos from the Admin panel.

📷

No photos yet

Photos will appear here as the project progresses.

Project Documents

Daily sign-in sheets, weekly safety meetings, and SWPPP (Stormwater Pollution Prevention Plan) documents. Admin uploads from the Admin panel.

📂

No documents yet

Documents will appear here as they are uploaded.

Project Progress

Overall Completion0%
Wk 1 — Concrete & Drainage
0%
Wk 2 — Demo & Base
0%
Wk 3 — Crack Fill & Repairs
0%
Wk 4 — Poly Guard & Paving
0%
Wk 5 — Striping & Closeout
0%
🚧

No updates yet

Progress updates will appear here once the project begins.

Field Notes

Observations, issues, RFIs, daily logs — added during construction via the Admin panel.

📝

No field notes yet

Admin Panel

Post Progress Update

📷

Click or drag photos here

📂 Upload Document

Daily sign-in sheets, safety meeting notes, SWPPP inspection reports. PDFs preferred; PNG/JPG/DOC also accepted.

📂

Click or drag file here (PDF, image, or Office doc)

🗂 Manage Documents

View or delete uploaded documents.

No documents uploaded yet.

📷 Upload Photos

Up to 5 photos at a time. Auto-compressed for fast upload from phone.

📈 Update Progress

📝 Add Field Note

📝 Manage Field Notes

No field notes yet.

🗒 Manage Updates

No updates posted yet.